Tower Crane Dismantling Method Statement ((new)) «Browser SAFE»

Conduct a pre-start toolbox talk with all personnel to review tasks, hazards, and emergency procedures.

Five-point fall arrest harnesses with double lanyards (mandatory for upper tower work).

[ Site Manager ] │ [ Lifting Supervisor ] │ ┌───────────────────┴───────────────────┐ ▼ ▼ [ Rigging Team ] [ Crane Operators ] (Slingers & Signallers) (Tower & Assist Cranes)

Rig the specified counter-weight blocks using tested chain slings. tower crane dismantling method statement

Unbolt the high-tensile fishplate bolts or drive out the mast pins connecting it to the lower section.

Tower Crane Dismantling Method Statement: Complete Step-by-Step Safe Work Procedure

Using the auxiliary mobile crane.

Once the last piece is on the ground, the method statement requires:

The exact sequence varies by crane type (topless, flat-top, or hammerhead) and dismantling method (mobile crane assisted, self-lowering, or helicopter). Below is the most common for a freestanding tower crane.

Confirm the tower crane's electrical supply can be isolated and locked out when required. 5. Step-by-Step Dismantling Procedure Conduct a pre-start toolbox talk with all personnel

Verify valid calibration certificates for all lifting gear (slings, shackles, chains).

The slewing unit, which contains the rotation mechanism, is removed along with the operator's cab. On some cranes, these may be removed together or separately.

Take the load strain, then remove the remaining counterweight blocks left for balance. Disconnect the counter-jib tie rods. Unbolt the high-tensile fishplate bolts or drive out

: Use of radio services for coordination between operators, supervisors, and riggers. SafeWork NSW 2. Pre-Dismantling Preparation

A minimum safety margin of 20% over the heaviest single component weight (usually the counter-jib or slewing platform). 4.3 Documentation and Tool Check